Comments (6)
I can't reproduce the problem.
Setting the planned schedule:
Save.
Register the work done:
Everything is as expected:
from pmis.
When creating a new task, the remaining time automatically replaces the scheduled time.
I do not complete the remaining time, what more as typing the hours worked it is the remaining time I appear in the minus.
I am using the version available on odoo.com
https://www.youtube.com/watch?v=KgTiGeep8eg
https://www.youtube.com/watch?v=b_hCW__ZVag
https://www.youtube.com/watch?v=lrZtXTH9Rf4
from pmis.
The remaining time is the difference between the planned time and worked time, so it's normal, that with a new task, where the worked time is still 0, the remaining time results the same as the planned time.
The remaining time is not meant to be edited manually except for the reasons of corrections (example: we initially planned less time than needed, so we correct the remaining time when and if we review the task). Don't touch the remaining time field on newly created task.
from pmis.
In the default time module, the time worked on the remaining time is redesigned.
Https://www.youtube.com/watch?v=TFp4LuCmxTM
After installing PMI differently to the department:
- I do not understand why after entering the overworked time the remaining time is in the negative. (After 2 hours of work, 2 hours remaining)
Https://www.youtube.com/watch?v=KgTiGeep8eg - I do not understand why it does not change or change without appearing at scheduled times.
https://www.youtube.com/watch?v=b_hCW__ZVag
from pmis.
The activity scheduling considers the activity duration field and not the "initially planned hours" since at time it was designed without considering the use of the settings/project option "Manage time estimation on tasks". So to mimic the same functionality as you were used to you just need to set the "Activity duration" field instead of the "Initialy planned hours".
from pmis.
There's another thing to consider:
In the tasks (activities) you have 2 planned times (task form, tab other settings).
-
Activity duration - planned calendar time, like, I plan we'll finish in 40 hours (5 days) from start, but it doesn't mean, that we'll work for 40 hours - TIME PLANNING
-
Initially Planned Hours - cost man hours planned for that activity, like - even, if we'll finish it in 40 hours, we'll actually invest only 5 hours of real work (like 1 hr every day) - COST PLANNING
The Limitations section in that same tab defines the initial calculation data - fill only one of them, depending on your limitations for that task:
-
earliest start date - we can't start before that date, but we can start on that date or later
-
latest finish date - do whatever you want, but we have to finish until then
Based on those limits (and task relationships - predecessor and successor tasks) and the duration field the button calculate network calculates the optimal dates for the entire task network (a group of interconnected tasks).
from pmis.
Related Issues (15)
- Other modules? HOT 1
- Problem installing project_easy_sheduling_tool HOT 1
- Error during pmis installation HOT 3
- Error: using create_wbs_element before declaration in v8.0 HOT 1
- Error: null value in column "name" violates not-null constraint when installing project_wbs_gtd v8.0 HOT 2
- There is no "planned hours" field when opening or editing a task HOT 1
- Gantt view HOT 2
- Branch to 9.0 HOT 1
- Erro on install v8 HOT 2
- how to install pmis HOT 1
- Question: compatible with odoo.sh
- project_wbs is not migrated to 10.0 HOT 1
- Confirmation of analytic resource plan - version to be used HOT 1
- Analytic plan version form view does not show labels
Recommend Projects
-
React
A declarative, efficient, and flexible JavaScript library for building user interfaces.
-
Vue.js
🖖 Vue.js is a progressive, incrementally-adoptable JavaScript framework for building UI on the web.
-
Typescript
TypeScript is a superset of JavaScript that compiles to clean JavaScript output.
-
TensorFlow
An Open Source Machine Learning Framework for Everyone
-
Django
The Web framework for perfectionists with deadlines.
-
Laravel
A PHP framework for web artisans
-
D3
Bring data to life with SVG, Canvas and HTML. 📊📈🎉
-
Recommend Topics
-
javascript
JavaScript (JS) is a lightweight interpreted programming language with first-class functions.
-
web
Some thing interesting about web. New door for the world.
-
server
A server is a program made to process requests and deliver data to clients.
-
Machine learning
Machine learning is a way of modeling and interpreting data that allows a piece of software to respond intelligently.
-
Visualization
Some thing interesting about visualization, use data art
-
Game
Some thing interesting about game, make everyone happy.
Recommend Org
-
Facebook
We are working to build community through open source technology. NB: members must have two-factor auth.
-
Microsoft
Open source projects and samples from Microsoft.
-
Google
Google ❤️ Open Source for everyone.
-
Alibaba
Alibaba Open Source for everyone
-
D3
Data-Driven Documents codes.
-
Tencent
China tencent open source team.
from pmis.