Earned Value Management (EVM) Calculation Plugin

Rate at redmine.org

This plugin provides the function of calculating evm of projects . EVM can help you to track your project progress and its status and to forecast the future performance of the project.

Current Version

5.3.5

Compatibility

Redmine 4.0.0 and above

For those who like highchart graph display

Charts are displayed using Chart.js from Version 5.0. Use the following version for Highcharts graph display. https://github.com/momibun926/redmine_issue_evm/releases/tag/4.6

Notification

The redmine3.4.x compatible version in branch "redmine3-4-3". https://github.com/momibun926/redmine_issue_evm/tree/redmine3-4-3

Main features

  • Calculate EVM with chart
    • All projects with ES
    • Each version
    • Each asssignee (Shown estimated hours each days on chart)
    • Each parent issues
    • Some Tarckers
  • Project metrics
    • Duration
    • Satus
    • Days until due date
    • Amount of calculation issues
    • Variance at baseline
    • Amount of issue. (version, assignee, tracker)
    • Chart of EVM(PV,EV,AC), Forecast is invalid when project is finished.
  • Common setting
    • Basic time of day
    • Calculation method of ETC
    • Forcast chart, Performance chart, Threthold value, incomplete issues
  • Create baselines, and view history

How to calculate EVM

The below are used for EVM.

  • start date
  • due date (If empty, effective of version)
  • estimated time (If you set it as 0, you will not get PV, CV)
  • spent time

If you input these into your project, it can help you to calculate both a single issue’s EVM and whole project’s one.

  • PV: Dividing estimated time by the days (from start date to due date(or effective date of version )) to get daily workload
  • EV: After issues are closed, you can get EV. When the progress rate is set, it is calculated by estimated time. (progress rate on the day when the progress is set.)
  • AC: Total work hours of PV issues.

Example

(1) Create an issue with:

  • start date: 2015/08/01
  • due date: 2015/08/03
  • estimated time: 24 hours

At that time, only PV is calculated. As you have not closed the issue yet, EV equals 0. PV: Dividing estimated time: 24hours by 3 days (from start date to due date)

EVM 8/1 8/2 8/3
PV 8 16 24
EV 0 0 0
AC 0 0 0

(2) Input your spent time.

8/1: 10.0hours 8/2: 6.0hours 8/3: 8.0hours

EVM 8/1 8/2 8/3
PV 8 16 24
EV 0 0 0
AC 10 16 24

(3) After finishing the issue, close it on 8/3. EV will be calculated on 8/3.

EVM 8/1 8/2 8/3
PV 8 16 24
EV 0 0 24
AC 10 16 24

Based on these data, EVM and chart are created.

Baseline

If you set baseline, you can know easily how project divergence is and whether new task (issues) can be added by chart. In other words, you can see whether your estimated daily workload is over or not by chart. PV is based on your baseline. In addition, you can set calculation without baseline by options.

View options

  • Change the calculating basic date
  • Using baseline
  • Explanation of EVM

About workig days

  1. Excluding weekends and holidays
  2. If it is only weekends or holidays, make it a working day
  3. Use holidays gem -> Regional settings are set in the common setting page(common setting link in contextial)

Example)

In Japan, May 3, May 4, May 5 are holidays

  • Including weekends and holidays
Start date Due date Estimated time Working day PV per day
May 1, 2017 (Monday) May 8, 2017 (Monday) 12 hours 3 days 4 hours
  • Including only a few weekends and holidays
Start date Due date Estimated time Working day PV per day
May 1, 2017 (Monday) May 7, 2017 (Sunday) 10 hours 2 days 5 hours
  • Only weekends and holidays
Start date Due date Estimated time Working day PV per day
May 3, 2017 (Wed) May 7, 2017 (Sunday) 20 hours 5 days 4 hours

Chart

Charts are displayed using Chart.js. This java scripts include Redmine.

Main chart

Show PV,EV,AC with baseline. Display unclosed issues according to the baseline.

Performance chart

Show SPI,CPI,CR of the days involved with PV,EV,AC

Installation

(1) Getting plugin source

case of zip file.

  • Download zip-file
  • Create a folder named redmine_issue_evm under [redmine_root]/plugins/
  • Extract zip file in redmine_issue_evm

Case of git clone.

git clone git://github.com/momibun926/redmine_issue_evm [redmine_root]/plugins/redmine_issue_evm

(2) bundle install

bundle install

(3) Migration. At the command line type

rake redmine:plugins:migrate NAME=redmine_issue_evm RAILS_ENV=production

(4) Restart your Redmine web servers (e.g. mongrel, thin, mod_rails).

(5) Login and configure the plugin (see Permissions section, Administration->plugin)

UnInstall

rake redmine:plugins:migrate NAME=redmine_issue_evm VERSION=0

Screen shots

Overview evm sample screenshot

Assignees evm sample screenshot

Prent issues evm sample screenshot

Trackers evm sample screenshot

Create baseline evm sample screenshot

Baseline History evm sample screenshot

Plugin Setting evm sample screenshot

Contributing

  1. Fork it
  2. Create your feature branch (git checkout -b my-new-feature)
  3. Commit your changes (git commit -am 'Add some feature')
  4. Push to the branch (git push origin my-new-feature)
  5. Create new Pull Request

My Environment

  • Redmine version 4.1.1.stable
  • Ruby version 2.5.8-p224 (2020-03-31) [x86-64-linux]
  • Rails version 5.2.4.2
  • Environment production
  • Database adapter Mysql2
  • Mailer queue ActiveJob::QueueAdapters::AsyncAdapter
  • Mailer delivery smtp

Translators

I appreciate your cooperation, Wen Wen, Shen.

redmine_issue_evm's People

Contributors

momibun926 avatar alexandermeindl avatar archonwang avatar yusuken1983 avatar

Recommend Projects

  • React photo React

    A declarative, efficient, and flexible JavaScript library for building user interfaces.

  • Vue.js photo Vue.js

    🖖 Vue.js is a progressive, incrementally-adoptable JavaScript framework for building UI on the web.

  • Typescript photo Typescript

    TypeScript is a superset of JavaScript that compiles to clean JavaScript output.

  • TensorFlow photo TensorFlow

    An Open Source Machine Learning Framework for Everyone

  • Django photo Django

    The Web framework for perfectionists with deadlines.

  • D3 photo D3

    Bring data to life with SVG, Canvas and HTML. 📊📈🎉

Recommend Topics

  • javascript

    JavaScript (JS) is a lightweight interpreted programming language with first-class functions.

  • web

    Some thing interesting about web. New door for the world.

  • server

    A server is a program made to process requests and deliver data to clients.

  • Machine learning

    Machine learning is a way of modeling and interpreting data that allows a piece of software to respond intelligently.

  • Game

    Some thing interesting about game, make everyone happy.

Recommend Org

  • Facebook photo Facebook

    We are working to build community through open source technology. NB: members must have two-factor auth.

  • Microsoft photo Microsoft

    Open source projects and samples from Microsoft.

  • Google photo Google

    Google ❤️ Open Source for everyone.

  • D3 photo D3

    Data-Driven Documents codes.